Construction updates
Vision

Construction updates

Keep up-to-date with the latest construction milestones at each stage of development.

JULY 2022

We’re currently constructing almost 700  lots over 15 stages – 48, 54-60, 65-67 (including Townhouses) as well as Central Quarter Townhouses stages 1-4. This level of work is almost three times of where we were sitting this time last year! All works are on schedule with our first three stages (stages 51-53) titling in the past month.

Bonniebrook Bridge

The future main access point from Bonniebrook through to Aintree is progressing well & remains on track to open later in the year. We are pleased to share that kerb installation is now underway as well as final electrical & painting works.

Secondary School site

Earthworks and sewer construction are well underway on Aintree Secondary School (interim name). Works are tracking on schedule with construction by the Victorian School Building Authority expected to commence next year with a 2024 school opening.

Leakes Rd & Woodlea Blvd intersection update

Phase two of the Project is well underway with the remaining roundabout section’s being removed during June. Pavement construction will begin for the northbound & southbound lanes, with the use of the temporary road along Leakes Road to allow for 2 lanes to remain open. Periodic shuttle flow (Stop/Slow) will be used to control the flow of traffic during high construction work times (10am – 3pm).

  • Phase 1: authority approvals

    Obtaining approval from Council and other service authorities for the detailed engineering plans.

  • Phase 2: earthworks

    Construction of earth works. This involves cutting and filling in order to achieve suitable surface levels.

  • Phase 3: sewer & drainage

    Construction of sewer and drainage services.

  • Phase 4: water, gas & road excavation

    Construction of initial road works and installation of water and gas services.

  • Phase 5: electrical & telecommunications

    Construction of road kerbs and installation of electrical and telecommunication services.

  • Phase 6: road pavements & concreting

    Finalisation of road construction and the installation of footpaths, crossover and top soil.

  • Phase 7: compliance inspections

    Inspections and signoffs by Council and relevant service authorities to achieve Statement of Compliance.

  • Phase 8: title registration

    Registration of lots with Land Titles Office. Certificates of Title are issued for each individual lot followed by Settlement of lots within 14 days.

Stages 02-39

  • Titled & settled

Stage 40

  • Titled & settled

Stage 41

  • Titled & settled

Stage 42

  • Titled & settled

Stage 43

  • Titled & settled

Stage 44

  • Titled & settled

Stage 45

  • Titled & settled

Stage 46

  • Titled & settled

Stage 47

  • Titled & settled

Stage 48

  • Phase 6: road pavements & concreting
  • Expected titles August 2022

Stage 49

  • Titled & settled

Stage 50

  • Titled & settled

Stage 51

  • Titled & settled

Stage 52

  • Titled & settled

Stage 53

  • Titled & settled

Stage 54

  • Phase 7: Compliance inspections
  • Expected titles August 2022

Stage 55

  • Phase 6: road pavements & concreting
  • Expected titles October 2022

Stage 56

  • Phase 6: road pavements & concreting
  • Expected titles November 2022

Stage 57

  • Phase 5: Electrical & Telecommunications
  • Expected titles December 2022

Stage 58

  • Phase 3: Sewer & drainage
  • Expected titles January 2023

Stage 59

  • Phase 3: Sewer & drainage
  • Expected titles March 2023

Stage 60

  • Phase 3: Sewer & drainage
  • Expected titles February 2023

Stage 61

  • Phase 1: Authority Approvals
  • Expected titles February 2024

Stage 62

  • Phase 1: Authority Approvals
  • Expected titles December 2023

Stage 65

  • Phase 2: Earthworks
  • Expected titles June 2023

Stage 66

  • Phase 2: Earthworks
  • Expected titles August 2023

Stage 67

  • Phase 2: Earthworks
  • Expected titles October 2023

Stage 1

  • Phase 6: road pavements & concreting
  • Expected titles August/September 2022
  • Townhouse construction to commence following titles

Stage 2

  • Phase 5: Electrical & Telecommunications
  • Expected titles August 2022
  • Townhouse construction to commence following titles

Stage 3

  • Phase 3: Sewer & drainage
  • Expected titles December 2022
  • Townhouse construction to commence following titles

Stage 4

  • Phase 3: Sewer & drainage
  • Expected titles March 2023
  • Townhouse construction to commence following titles

* The title date estimates provided are based on current information regarding the design, construction and authority approvals timeframes for that particular stage. Woodlea uses this information to provide a best estimate of the month which titles will be achieved however this is subject to change and is often influenced by factors which are often outside of Woodlea’s control such as weather, contractor delays and authority inspections. We reiterate that the title dates provided are an estimate only and are subject to change.

Register for Woodlea updates

Register for Woodlea updates

Be the first to know about new releases, VIP events, and receive your free eBook on Melbourne’s fastest growing community.

Register now