Construction updates
Vision

Construction updates

Keep up-to-date with the latest construction milestones at each stage of development.

Latest Community Update

It’s a big year for land under construction at Woodlea with 8 stages currently under construction. The team have been working hard to deliver Stages 63, 68 – 70 as well as TCS5, TCS6, TCS7 & stage 74, all of which are tracking on schedule. We have had a massive 586 lots title this calendar year with a busy year of activity ahead! 

Secondary School site

Works surrounding the school site are complete. Construction of the intersection of Taylors Road is nearing completion opening up access to the school site from Taylors Road, ready for the first cohort of Year 7 students for term 1 of 2024.

Park maintenance

A friendly reminder that any maintenance, damage or other issues that need addressing around the community (particularly our parks) should be submitted via the ‘snap send solve’ app. We are aware of some of these concerns but with ownership/maintenance sitting with council we encourage our residents to report & advocate for Aintree directly to the City of Melton.

  • Phase 1: authority approvals

    Obtaining approval from Council and other service authorities for the detailed engineering plans.

  • Phase 2: earthworks

    Construction of earth works. This involves cutting and filling in order to achieve suitable surface levels.

  • Phase 3: sewer & drainage

    Construction of sewer and drainage services.

  • Phase 4: water, gas & road excavation

    Construction of initial road works and installation of water and gas services.

  • Phase 5: electrical & telecommunications

    Construction of road kerbs and installation of electrical and telecommunication services.

  • Phase 6: road pavements & concreting

    Finalisation of road construction and the installation of footpaths, crossover and top soil.

  • Phase 7: compliance inspections

    Inspections and signoffs by Council and relevant service authorities to achieve Statement of Compliance.

  • Phase 8: title registration

    Registration of lots with Land Titles Office. Certificates of Title are issued for each individual lot followed by Settlement of lots within 14 days.

Stages 1-61 & 65-66, TCS2, TCS3, TCS4 & TCS8

  • Titled & settled

Stage 62

  • Phase 8: Title Registration
  • Expected titles December 2023

Stage 63

  • Phase 4: Water, Gas & Road Excavation
  • Expected titles March 2024

Stage 67

  • Phase 8: Title Registration
  • Expected titles December 2023

Stage 68

  • Phase 3: Sewer & Drainage
  • Expected titles 2nd Quarter 2024

Stage 69

  • Phase 2: Earthworks
  • Expected titles 3rd Quarter 2024
Stage TCS5
  • Phase 6: Road Pavements & Concreting
  • Expected titles January 2024

Stage TCS6

  • Phase 5: Electrical & Telecommunications
  • Expected titles January 2024

Stage TCS7

  • Phase 2: Earthworks
  • Expected titles 3rd Quarter 2024

Stage 70

  • Phase 1: Authority Approvals
  • Expected titles 1st Quarter 2025

* The title date estimates provided are based on current information regarding the design, construction and authority approvals timeframes for that particular stage. Woodlea uses this information to provide a best estimate of the month which titles will be achieved however this is subject to change and is often influenced by factors which are often outside of Woodlea’s control such as weather, contractor delays and authority inspections. We reiterate that the title dates provided are an estimate only and are subject to change.