Construction updates
Vision

Construction updates

Keep up-to-date with the latest construction milestones at each stage of development.

Latest Community Update

It’s a big year for land at Woodlea. Land currently under construction includes Stages 68A, 69, 70, 71, 72 & 75, all of which are on schedule. We expect over 170 land lots to title this year!

New Wetlands Park

Inspired by the beauty of its natural surroundings, the park will feature stunning dandelion-inspired structures, soaring up to five meters into the sky, with plenty of natural play elements to spark imaginative play. Opening in early 2025, the park will coincide with the launch of our new Display Village and Sales Hub, seamlessly connected by pedestrian bridges linking the two sites.

 

Secondary School site

Yarrabing Secondary College & Dharra Specialist School have proudly welcomed their first pupils! Both schools are a central component of Woodlea’s new Sports and Education Precinct, adding to the existing playgroup, two childcare centres, and two primary schools already within the estate. The intersection of Taylors Road is also complete, opening up access to the school site from Taylors Road.

 

New Display Village & Sales Centre

Opposite the Active Open Space precinct will stand the brand-new Woodlea Display Village, featuring 17 builders and 39 display homes. Nestled within this new Display Village will be our final legacy Sales Centre, which is already making significant progress. The frame has been installed, with construction on the roof commencing this week. The completed product will be our most impressive sales office yet and provide customers with an industry-leading sales journey experience. Stay on the lookout for more updates! 

 

 

Active Open Space (AOS) precinct

Construction of the AOS precinct is underway with two fields opening at the end of 2024. The carpark and sports fields are already complete, and works on the sports pavilion have started, with the surrounding landscaping to take shape over the next couple of months. Upon completion, the AOS precinct will feature a brand new sports pavilion, skate park, all abilities playground, BBQ facilities plus a large dog park.

Park maintenance

A friendly reminder that any maintenance, damage or other issues that need addressing around the community (particularly our parks) should be submitted via the ‘snap send solve’ app. We are aware of some of these concerns but with ownership/maintenance sitting with council we encourage our residents to report & advocate for Aintree directly to the City of Melton.

  • Phase 1: authority approvals

    Obtaining approval from Council and other service authorities for the detailed engineering plans.

  • Phase 2: earthworks

    Construction of earth works. This involves cutting and filling in order to achieve suitable surface levels.

  • Phase 3: sewer & drainage

    Construction of sewer and drainage services.

  • Phase 4: water, gas & road excavation

    Construction of initial road works and installation of water and gas services.

  • Phase 5: electrical & telecommunications

    Construction of road kerbs and installation of electrical and telecommunication services.

  • Phase 6: road pavements & concreting

    Finalisation of road construction and the installation of footpaths, crossover and top soil.

  • Phase 7: compliance inspections

    Inspections and signoffs by Council and relevant service authorities to achieve Statement of Compliance.

  • Phase 8: title registration

    Registration of lots with Land Titles Office. Certificates of Title are issued for each individual lot followed by Settlement of lots within 14 days.

Stages 1-63 & 65-68, 74, 78A, TC6 & TC8

  • Titled & settled

Stage 68A

  • Phase 2: Earthworks
  • Expected titles 2nd Quarter 2025

Stage 69

  • Phase 7: Compliance Inspections
  • Expected titles November 2024

Stage 70

  • Phase 6: Road Pavements & Concreting
  • Expected titles March 2025

Stage 71

  • Phase 4: Water, Gas & Road Excavation
  • Expected titles May 2025

Stage 72

  • Phase 2: Earthworks
  • Expected titles 3rd Quarter 2025

Stage TC7

  • Phase 8: Title Registration
  • Expected titles November 2024

* The title date estimates provided are based on current information regarding the design, construction and authority approvals timeframes for that particular stage. Woodlea uses this information to provide a best estimate of the month which titles will be achieved however this is subject to change and is often influenced by factors which are often outside of Woodlea’s control such as weather, contractor delays and authority inspections. We reiterate that the title dates provided are an estimate only and are subject to change.

Register for Woodlea updates

Register for Woodlea updates

Be the first to know about new releases, VIP events, and receive your free eBook on Melbourne’s fastest growing community.

Register now