Construction
Updates

January 2019

With almost 2,800 residents living at Woodlea & another 530 homes under construction, 2019 is going to be a massive year ahead! We're very excited to announce the opening of Bacchus Marsh Grammar Primary School next month, followed closely by the Woodlea Early Learning Chidcare Centre! Also, stay tuned for an EPIC update on our Town Centre planned for 2020 coming soon!

Phase 1: Authority Approvals
Obtaining approval from Council and other service authorities of the detailed engineering plans.
Phase 2: Earthworks
Construction of earth works. This involves cutting and filling in order to achieve suitable surface levels.
Phase 3: Sewer & Drainage
Construction of sewer and drainage services.
Phase 4: Water, Gas & Road Excavation
Construction of initial road works and installation of water and gas services.
Phase 5: Electrical & Telecommunications
Construction of road kerbs and installation of electrical and telecommunication services.
Phase 6: Road Pavements & Concreting
Finalisation of road construction and the installation of footpaths, crossovers and top soil.
Phase 7: Compliance Inspections
Inspections and sign offs by Council and relevant service authorities in order to achieve Statement of Compliance.
Phase 8: Title Registration
Registration of lots with Land Titles Office. Certificates of Title are issued for each individual lot followed by Settlement of lots within 14 days.

Anticipated
title dates

Stages 02-09

View updates

Stage 02

  • Titled & settled

Stage 03

  • Titled & settled

Stage 04

  • Titled & settled

Stage 05

  • Titled & settled

Stage 06

  • Titled & settled

Stage 07

  • Titled & settled

Stage 08

  • Titled & settled

Stage 09

  • Titled & settled

Stages 10-19

View updates

Stage 10

  • Titled & settled

Stage 11

  • Titled & settled

Stage 12

  • Titled & settled

Stage 13

  • Titled & settled

Stage 14

  • Titled & settled

Stage 15

  • Titled & settled

Stage 16

  • Titled & settled

Stage 17

  • Titled & settled

Stage 18

  • Titled & settled

Stage 19

  • Titled & settled

Stages 20-29

View updates

Stage 20

  • Titled & settled

Stage 21

  • Titled & settled

Stage 22

  • Titled & settled

Stage 23

  • Titled & settled

Stage 24

  • Titled & settled

Stage 25

  • Titled & settled

Stage 26

  • Titled & settled

Stage 27

  • Titled & settled

Stage 28

  • Titled & settled

Stage 29

  • Phase 7: Compliance Inspections
  • Expected titles Febuary 2019

Stages 30-39

View updates

Stage 30

  • Phase 8: Title Registration
  • Titled. Settlements due 31st January

Stage 31

  • Phase 6: Road Pavements & Concreting
  • Expected titles March 2019

Stage 32

  • Phase 4: Water, Gas & Road Excavation
  • Expected titles May 2019

Stage 33

  • Phase 4: Water, Gas & Road Excavation
  • Expected titles May 2019

Stage 34

  • Phase 4: Water, Gas & Road Excavation
  • Expected titles July 2019

Stage 35

  • Phase 3: Sewer & Drainage
  • Expected September 2019

Stage 36

  • Phase 3: Sewer & Drainage
  • Expected titles October 2019

Stage 37

  • Phase 3: Sewer & Drainage
  • Expected titles October 2019

Stage 38

  • Phase 6: Road Pavements & Concreting
  • Expected titles April 2019

Stage 39

  • Phase 2: Earthworks
  • Expected titles December 2019

Stage 40

View updates

Stage 40

  • Phase 1: Authority Approvals
  • Expected titles March 2020

Other

View updates

Taylors Rd Phase 1

Open to public

Taylors Road Phase 2

Taylors Road Phase 2 - Pavement construction is progressing well. Estimated for completion in the second quarter of 2019.

Find out more