November Construction Update

We've had such a busy few months at Woodlea with so many great events as well as construction milestones achieved. Recent events have seen our community come together to enjoy our fourth annual Soccer Clinic as well as the formation of  the Aintree Community Sports Association. We're excited to see the community become even fitter! The team are very grateful to be bringing you this month's news and we look forward to wrapping up what has been a momentous year for Woodlea. 

Stages 2 – 25, 27 and 28 - Titled and settled

Stage 26 – Statement of Compliance Received - Expected titles December 2018
Stage 26 is located south of Stage 24 and abuts the future Local Town Centre to the south. Statement of Compliance has been achieved and titles are currently being lodged at the Land Titles Office.


Stage 29 - Expected titles January 2019
Stage 29 is nearing completion with the final intersection paving expected to be completed by early December. Consent to register titles are currently being procured from Council and service authorities.


Stage 30 - Expected titles January 2019
Stage 30 is located south of Stage 23, north of the Local Town Centre precinct and comprises the Stage 30 neighbourhood park. Civil construction works have been completed and consent to register titles is currently being procured from utility authorities and Council.

 

Stage 31 - Expected titles February 2019
Stage 31 is located directly north of the Deanside wetlands, south-east of the future Local Town Centre precinct and includes a neighbourhood park. Water installation is complete with electrical and NBN commencing shortly.

 

Stage 32 - Expected titles March 2019
Stage 32 is located to the east of Stage 30 and the future Local Town Centre precinct. Sewer and drainage works are complete whilst water and gas works have commenced.

 

Stage 33 - Expected titles April 2019
Stage 33 is located north of Stage 31 and the Deanside wetlands, and east of the future Local Town Centre precinct. Sewer and drainage works are complete and road excavation has commenced.

 

Stage 34 - Expected titles June 2019
Stage 34 is located north of Stage 35, east of the of the future Local Town Centre precinct and will also comprise the Stage 34 neighbourhood park. Sewer works are complete with water installation commencing.

 

Stage 35 - Expected September 2019
Stage 35 is located north of Stage 33, the Deanside wetlands and to the east of the future Local Town Centre precinct. Bulk earthworks are complete whilst sewer and drainage works have commenced.

 

Stage 36 – Expected titles October 2019
Stage 36 is located directly south of the Aintree Wetland. Earthworks are completed and sewer installation has commenced.

 

Stage 37 - Expected titles July 2019
Stage 37 is located directly north-west of the future Local Town Centre precinct and north of the Active Open Space playing fields. Bulk earthworks are complete and sewer works have commenced.

 

Stage 38 - Expected titles March 2019
Stage 38 is located north of the Stage 23 raingarden at the intersection of Taylors Road and Frontier Avenue. Stage 38 will contain the new Woodlea Display Village including a feature park. Sewer works are complete with drainage works are nearing completion. Road excavation is complete and water installation is progressing.

 

Stage 39 – Expected titles December 2019
Stage 39 is located directly east of the government primary school. Bulk earthworks are complete and sewer works are commencing shortly.

 

Taylors Road Phase 1 – Opening Soon
Taylors Road Phase 1 - Involves the construction of a new single carriageway (one lane in each direction) from Leakes Road to Frontier Avenue adjacent to Stage 18 accessed via a left out/right in intersection. As part of the project, a new un-signalised T-intersection will be formed on Leakes Road at the entrance to Taylors Road. This involves the widening and reconstruction of Leakes Road on both north and south approaches along with the construction of raised concrete splitter islands and new line markings. Civil construction works have been completed and the road will soon be opened to traffic upon energisation of the road lighting.

 

Taylors Road Phase 2 – Forecasted Completion 2nd Quarter 2019
Taylors Road Phase 2 - Includes the section of carriageway from Frontier Avenue to Fields Street. Pavement construction is processing well. Estimated for completion in the second quarter of 2019.