Woodlea Construction Update

If you haven’t been to Woodlea in a while, you will be pleasantly surprised to see the first new homes going up!

Builders are well underway constructing our thirty-seven home display village in Stage 1.  The village is anticipated to open in May next year and will feature our new sales centre plus a café, general store and community hub. The playground and park in Stage 1 is under construction and will open for residents by May 2016.

Located adjacent to the display village will be the home of our first residents of Stage 2, which includes Arbourton Release 1. Titles were issued in October 2015 and residents will shortly be commencing construction on their homes.

Construction of Stage 3, comprises 78 lots and is located south of the display village. Construction is nearing completion with footpath and top soiling works remaining. Works are on track to achieve titles in January / February 2016.

Also south of the display village is Stage 4, comprising 63 blocks. Construction is well advanced with pavement preparation, kerb and channels and service reticulation complete. Footpath, road asphalting and top soiling is underway. Works are on track to achieve titles in February / March 2016.

Construction of Stage 5, comprises 58 lots is located east of the display village. Construction is well advanced with bulk earthworks, sewer, water, gas, pavement preparation and kerb and channel complete. Electrical and NBN reticulation is also complete with footpath works now commenced. Works are on track to achieve titles in March 2016

Construction of the 97 lots in Stage 6, located south of Stage 4, commenced in early September with bulk earthworks, sewer and drainage complete. Pavement preparation and water and gas main reticulation has commenced. Works are on track to achieve titles in July 2016

Construction of the 46 lots in Stage 7 commenced in early October with bulk earthworks close to completion. Drainage reticulation has commenced. Works are on track to achieve titles in August 2016.

Construction of Stage 8, comprises 53 lots and is located south of the display village. Construction has just commenced with bulk earthworks underway. Works are on track to achieve titles in September 2016.

Planning for the local town centre is underway with discussions being held with various operators.