Construction update - September 2017

It's been a busy month of construction activity at Woodlea and there has never been a more exciting time to be part of our community. Our Active Open Space precinct is now complete, with final works on the sports pavilion also nearing completion, ready for a November launch! Both football ovals were grassed over the weekend, and we look forward to many future sporting seasons ahead - commencing Spring 2018. Get your full construction and titles update below.

Stages 2 – 16 and 19 are titled and settled

Stage 17 - Expected titles early October 2017

Stage 17 is located north of the display village, and also abuts Stage 18 to the east. Construction has reached practical completion and final consent to register titles is currently being procured from utility authorities and Council.

Stage 18 - Expected titles October 2017

Stage 18 abuts Stage 17 to the west, and both Stages 5 and 16 to the south. Final road linemarking and concrete works are nearing completion.. Consent to register titles is currently being procured from utility authorities and Council

Stage 20 - Expected titles November 2017

Stage 20 is located north of the Local Town Centre and includes a neighbourhood park. Final lot shaping, road surfacing and footpath construction works are nearing completion. Consent to register titles from utility authorities and Council will commence shortly.

Stage 21 - Expected titles November 2017

Stage 21 is located east of Stage 20, and north of the Local Town Centre. Road construction is progressing well, with kerb and channel and electrical works commenced.

Stage 22 - Expected titles November 2017

Stage 22 is located south of Stages 20 and 21, and north of Stage 25 and the Local Town Centre. Water installation is complete with electrical works to commence shortly.

Stage 23 - Expected titles February 2018

Stage 23 is located east of Stage 21, and includes the feature raingarden. Sewer and drainage works are nearing completion and road construction has commenced.

Stage 24 - Expected titles February 2018

Stage 24 is located in close proximity to the Local Town Centre, south of Stage 23 and north of Stages 26 and 30. Sewer and drainage works are nearing completion. Installation of water is progressing well with road construction works due to commence shortly.

Stage 25 – Expected titles March 2018

Stage 25 is located south of Stage 22, and north of the Local Town Centre. Sewer works are nearing completion and drainage works are well progressed.

Stage 26 - Expected titles June 2018

Stage 26 is located south of Stage 24, and abuts the future Local Town Centre to the south. Bulk earthworks are nearing completion and sewer and drainage have commenced.

Stage 27 – Expected titles March 2018

Stage 27 is located east of Stage 23 and abuts the Kororoit Creek reserve. Taylors Road is located north of the stage. Bulk earthworks are progressing well and sewer works have commenced.

Stage 28 – Expected titles May 2018

Stage 28 is located east of Stage 23 and 24, and abuts the Kororoit Creek reserve to the east. Bulk earthworks are nearing completion and drainage works have commenced.

Stage 29 – Expected titles June 2018

Stage 29 is located north of Stage 32, and east of Stage 30. It also abuts the feature drainage reserve to the east. Construction of this stage is commencing in September.

Stage 30 – Expected titles July 2018

Stage 30 is located west of Stage 23, north of the Local Town Centre precinct and also comprises the Stage 30 neighbourhood park. Construction is due to commence in September 2017.

Stage 31 – Expected titles October 2018

Stage 30 is located west of Stage 26 and north of the Local Town Centre precinct. Construction is due to commence October 2017.

Active Open Space

Stage 1 of the Active Open Space precinct comprises of 1 AFL Oval, adventure playground, youth space and car parking. Construction works are now completed. Stage 2 of the Active Open Space comprises of a second AFL oval and 10 tennis courts and the sporting pavilion with construction completion estimated in November 2017. The ovals are expected to be ready for use in fourth quarter of 2018 following a 1 year establishment period of the grass playing surface.

Taylors Road

The first stage of Taylors Road involves the construction of a new single carriageway (one lane in each direction) from Leakes Road to Frontier Avenue adjacent to Stage 18 accessed via a left out/right in intersection

As part of the project, a new un-signalised Tee-intersection will also be formed on Leakes Road at the entrance to the new Taylors Road. This will involve the widening and reconstruction of Leakes Road on both north and south approaches along with the construction of raised concrete splitter islands and new line markings.

Bulk earthworks to the east of Leakes Road and along Taylors Road are complete and drainage works are progressing well with pavement works to commence shortly. The first stage of the project is estimated to be completed in the second quarter of 2018.

What’s happening at Woodlea