Thursday 22nd September 2016

Construction update - September 2016

Woodlea continues to evolve and it is great to welcome so many new residents and visitors into our community. We look forward to some very exciting milestones with the Stage 4 park, due for completion in December 2016, followed by the Stage 7 Park, Major Play and Active Open Space Precinct scheduled to open early 2017. If you haven't been to Woodlea in a while, be sure to pay us a visit and see what all the hype is about!

Stage 10 - Expected titles September 2016
Stage 10 is located south of the Active Open Space precinct. The Plan of Subdivision has been lodged at the Titles Office and is now awaiting registration.

Stage 11 - Expected titles - November 2016
Stage 11 is located south of the planned Bacchus Marsh Grammar Primary School and includes a neighbourhood park. The reticulation of services and kerb and channel are complete. The footpath and road preparation works are nearing completion.

Stage 12 - Expected titles November 2016
Stage 12 is located south of the future town centre precinct and adjacent to the Deanside Wetlands conservation area. Stage 12 is progressing closely behind Stage 11. The reticulation of services, and kerb and channel are complete. The footpath and road preparation works are nearing completion.

Stage 13 - Expected titles January 2017
Stage 13 is located south of stage 12 and adjacent to the Deanside Wetlands conservation area. The reticulation of sewer, water and drainage is complete and kerb and channel works are about to commence.

Stage 14 - Expected titles March 2017
Stage 14 is located south of stage 13 and adjacent to the Deanside Wetlands conservation area. Bulk earthworks are complete and sewer and drainage works have commenced.

Stage 15 - Expected titles November/December 2016
Stage 15 is located south of the display village, which includes the old Woodlea sales office. Construction works have progressed well, with titles now expected late November or December. The reticulation of services and kerb and channel are complete. Road preparation works have commenced and concrete footpath works about to commence.

Stage 16 - Expected titles May 2017
Stage 16 is located north of the Active Open Space precinct. Construction has commenced and bulk earthworks are underway.

Stage 17 - Expected titles June 2017
Stage 17 is located north of the display village. Construction is expected to commence in September 2016.

Stage 18 - Expected titles July 2017
Stage 18 abuts Stage 17 to the west, and both Stages 5 and 16 to the south. Construction is expected to commence in September 2016.

Stage 19 - Expected titles July 2017
Stage 19 will abut Stage 18 to the west and Stage 16 to the south. Construction is expected to commence in September 2016.

Stage 20 - Expected titles September 2017
Stage 20 is located north of the local town centre and includes a neighbourhood park. Construction is expected to commence in October 2016.

Stage 21 - Expected titles October 2017
Stage 21 is located east of Stage 20, and north of the local town centre. The stage also abuts the future Taylors Road to the north. Construction is expected to commence in November 2016.

Active Open Space
Civil earthworks are progressing in stage 1 of the Active Open Space sports facility comprising 1 AFL Oval, adventure playground, youth space and car parking with completion anticipated in the first half of 2017. Construction of stage 2 of the Active Open Space, comprising a second AFL oval and 10 tennis courts and the sporting pavilion has also commenced with expected completion in the 4th quarter of 2017!