Tuesday 25th October 2016

Construction Update - October 2016

Despite the difficult winter conditions, construction activity continues to BOOM at Woodlea with the Stage 4 Park, due for completion as early as December 2016! Our team of experts are also working very hard to deliver a brand new Stage 7 Park, Major Play and Active Open Space precinct in the first half of 2017. Please read below for a full construction and title update.

Stage 11 - Expected titles December 2016

Stage 11 is located south of the planned Bacchus Marsh Grammar Primary School and includes a neighbourhood park. The reticulation of services, construction of kerb and channel, and footpaths are complete. The road construction works are nearing completion and consent to register the titles is currently being procured from utility authorities and Council.

Stage 12 - Expected titles December 2016

Stage 12 is located south of the future town centre precinct and adjacent to the Deanside Wetlands conservation area. Stage 12 is progressing closely behind Stage 11. The reticulation of services, construction of kerb and channel and footpaths are complete. The road construction works are nearing completion and consent to register the titles is currently being procured from utility authorities and Council.

Stage 13 - Expected titles January 2017

Stage 13 is located south of stage 12 and adjacent to the Deanside Wetlands conservation area. The reticulation of services and construction of kerb and channel are complete, and road pavement preparatory works have commenced.

Stage 14 - Expected titles March 2017

Stage 14 is located south of stage 13 and adjacent to the Deanside Wetlands conservation area. Bulk earthworks are complete. Sewer reticulation is now complete drainage works are progressing well.

Stage 15 - Expected titles December 2016

Stage 15 is located south of the display village, which includes the old Woodlea sales office. The reticulation of services, construction of kerb and channel and footpaths are complete. Road pavement preparatory works are well progressed.

Stage 16 - Expected titles May 2017

Stage 16 is located north of the Active Open Space precinct. Bulk earthworks are nearing completion, with reticulation of sewer and drainage commencing shortly.

Stage 17 - Expected titles June 2017

Stage 17 is located north of the display village. Bulk earthworks have commenced, with reticulation of sewer and drainage commencing shortly.

Stage 18 - Expected titles June 2017

Stage 18 abuts Stage 17 to the west, and both Stages 5 and 16 to the south. Bulk earthworks have commenced, with reticulation of sewer and drainage commencing shortly.

Stage 19 - Expected titles June 2017

Stage 19 will abut Stage 18 to the west and Stage 16 to the south. Bulk earthworks have commenced, with reticulation of sewer and drainage commencing shortly.

Stage 20 - Expected titles September 2017

Stage 20 is located north of the local town centre and includes a neighbourhood park. Construction is expected to commence in November 2016.

Stage 21 - Expected titles October 2017

Stage 21 is located east of Stage 20, and north of the local town centre. The stage also abuts the future Taylors Road to the north. Construction is expected to commence in November 2016.

Stage 22 - Expected titles October 2017

Stage 22 is located south of Stages 20 and 21, and north of Stage 25 and the local town centre. Construction is expected to commence in December 2016.

Active Open Space

Stage 1 of the Active Open Space sports facility comprises of 1 AFL Oval, adventure playground, youth space and car parking with completion anticipated in the first half of 2017. Stage 2 of the Active Open Space comprising a second AFL oval and 10 tennis courts and the sporting pavilion with expected completion in the 4th quarter of 2017. Civil earthworks are now complete to both stages, the reticulation of services is well progressed and the carpark construction has commenced.