Thursday 30th November 2017

Construction update - November 2017

2017 has marked a momentous year of construction at Woodlea, with so many significant milestones and infrastructure delivered and complete. Our community continues to evolve, and we're delighted to have welcomed well over 1000 residents, this number increasing every week. We are very proud to have delivered our Active Open Space Precinct, featuring 2 footy ovals, our Major Play Adventure Park and 10 tennis courts, ready for a Summer of sport and outdoor activity ahead!

Stages 2 – 17 and 19 are titled and settled

Stage 18 - Expected titles January 2017

Stage 18 abuts Stage 17 to the west, and both Stages 5 and 16 to the south. Construction works have reached completion and consent to register titles is currently being procured from utility authorities and Council.

Stage 20 - Expected titles January 2017

Stage 20 is located north of the Local Town Centre and includes a neighbourhood park. Construction works have reached completion and consent to register titles is currently being procured from utility authorities and Council.

Stage 21 - Expected titles January/February 2018

Stage 21 is located east of Stage 20, and north of the Local Town Centre. Construction works are nearing completion and consent to register titles is currently being procured from utility authorities and Council.

Stage 22 - Expected titles January/February 2018

Stage 22 is located south of Stages 20 and 21, and north of Stage 25 and the Local Town Centre. Construction works are nearing completion and consent to register titles is currently being procured from utility authorities and Council.

Stage 23 - Expected titles February 2018

Stage 23 is located east of Stage 21, and includes the feature raingarden. Sewer, drainage and water main installation is complete and road construction work, electrical installation and concreting are progressing well.

Stage 24 - Expected titles March 2018

Stage 24 is located in close proximity to the Local Town Centre, south of Stage 23 and north of Stages 26 and 30. Electrical installation is nearing completion and road works are progressing well.

Stage 25 – Expected titles March 2018

Stage 25 is located south of Stage 22, and north of the Local Town Centre. Sewer and drainage works are complete and water main construction is progressing well.

Stage 26 - Expected titles June 2018

Stage 26 is located south of Stage 24, and abuts the future Local Town Centre to the south. Sewer works are nearing completion and drainage works are progressing well.

Stage 27 – Expected titles April 2018

Stage 27 is located east of Stage 23 and abuts the Kororoit Creek reserve. Taylors Road is located north of the stage. Sewer and drainage works are complete and watermain installation has recently commenced.

Stage 28 – Expected titles May 2018

Stage 28 is located east of Stage 23 and 24, and abuts the Kororoit Creek reserve to the east. Sewer and drainage works are complete and watermain installation has recently commenced.

Stage 29 – Expected titles June 2018

Stage 29 is located north of Stage 32, and east of Stage 30. It also abuts the feature drainage reserve to the east. Sewer works are nearing completion and drainage works have recently commenced.

Stage 30 – Expected titles July 2018

Stage 30 is located south of Stage 23, north of the Local Town Centre precinct and also comprises the Stage 30 neighbourhood park. Bulk earthworks are nearing completion and sewer works has recently commenced.

Stage 31 – Expected titles October 2018

Stage 31 is located directly north of the Deanside wetlands and south east of the of the future Local Town Centre precinct and also comprises the Stage 31 neighbourhood park. Construction is forecasted to commence in December 2017.

Stage 32 – Expected titles January 2019

Stage 32 is located to the east of Stage 30 and the future Local Town Centre precinct. Construction is forecasted to commence in January 2018.

Stage 33 – Expected titles March 2019

Stage 33 is located north of Stage 31 and the Deanside wetlands and to the east of the of the future Local Town Centre precinct. Construction is forecasted to commence in February 2018.

Stage 34 - Expected titles June 2019

Stage 34 is located north of Stage 33 and to the east of the of the future Local Town Centre precinct and also comprises the Stage 34 neighbourhood park. Construction is forecasted to commence in April 2018.

Stage 37 – Expected titles May 2019

Stage 37 is located directly north-west of the future Local Town Centre precinct and north of the Active Open Space Playing fields. Construction is forecasted to commence in May 2018.

Active Open Space

Stage 1 of the Active Open Space precinct comprises of one AFL Oval, adventure playground, youth space and car parking. Construction works are now completed. Stage 2 of the Active Open Space comprises of a second AFL oval and 10 tennis courts and the sporting pavilion with construction completion estimated in early 2018. The ovals are expected to be ready for use in fourth quarter of 2018 following a 1 year establishment period of the grass playing surface.

Taylors Road

The first stage of Taylors Road involves the construction of a new single carriageway (one lane in each direction) from Leakes Road to Frontier Avenue adjacent to Stage 18 accessed via a left out/right in intersection
As part of the project, a new un-signalised Tee-intersection will also be formed on Leakes Road at the entrance to the new Taylors Road. This will involve the widening and reconstruction of Leakes Road on both north and south approaches along with the construction of raised concrete splitter islands and new line markings.
Pavement construction is progressing well, traffic on Leakes road is expected to be changed over to the new widened eastern carriageway in December to allow construction of the Western carriageway to commence. The first stage of the project is estimated to be completed in the second quarter of 2018.

The second stage of the Taylors Road from Frontier Avenue to Fields Street is forecasted to commence in January 2018.