Wednesday 24th May 2017

Construction Update - May 2017

It's a very exciting time to be part of Woodlea as our community has truely come alive! Construction continues to BOOM with 15 Stages titled and settled, and Stage 16 anticipated early June. We've welcomed over 500 residents, with a total of 340 homes complete and under construction.  

Stages 2 – 15 are titled and settled

Stage 16 - Expected titles June 2017

Stage 16 is located north of the Active Open Space precinct. The Plan of Subdivision has been lodged at the Titles Office and is now awaiting registration.

Stage 17 - Expected titles July 2017

Stage 17 is located north of the display village, and also abuts Stage 18 to the east. Electrical, NBN and preparatory works for road construction are well progressed, kerb and channel construction is also progressing well.

Stage 18 - Expected titles August 2017

Stage 18 abuts Stage 17 to the west, and both Stages 5 and 16 to the south. Sewer and drainage works are now complete, with water and gas servicing works nearing completion. Preparatory works for road construction are also nearing completion.

Stage 19 - Expected titles June 2017

Stage 19 abuts Stage 18 to the west and Stage 16 to the south. The Plan of Subdivision has been lodged at the Titles Office and is now awaiting registration.

Stage 20 - Expected titles October 2017

Stage 20 is located north of the local town centre and includes a neighbourhood park. Installation of water and gas is progressing well and preparatory works for road construction has commenced.

Stage 21 - Expected titles October 2017

Stage 21 is located east of Stage 20, and north of the local town centre. Bulk earthworks are complete and sewer and drainage works are progressing well.

Stage 22 - Expected titles November 2017

Stage 22 is located south of Stages 20 and 21, and north of Stage 25 and the local town centre. Bulk earthworks are complete and sewer construction has commenced.

Stage 23 - Expected titles December 2017

Stage 23 is located east of Stage 21, and includes the feature raingarden. Bulk earthworks are nearing competition. Sewer and drainage works to commence shortly.

Stage 24 - Expected titles January 2018

Stage 24 is located in close proximity to the Local Town Centre, south of Stage 23 and north of Stages 26 and 30. Bulk earthworks have commenced and are progressing well.

Stage 25 – Expected titles February 2018

Stage 25 is located south of Stage 22, and north of the local town centre. Bulk earthworks have commenced and are progressing well.

Stage 26 - Expected titles March 2018

Stage 26 is located south of Stage 24, and abuts the future Local Town Centre to the south. Construction is expected to commence in June 2017.

Stage 27 – Expected titles March 2018

Stage 27 is located east of Stage 23 and abuts the Kororoit Creek reserve. Taylors Road is located north of the stage. Construction is due to commence in May 2017.

Stage 28 – Expected titles May 2018

Stage 28 is located east of Stage 23 and 24, and abuts the Kororoit Creek reserve to the east. Construction is due to commence in June 2017.

Stage 29 – Expected titles June 2018

Stage 29 is located north of Stage 32, and east of Stage 30. It also abuts the feature drainage reserve to the east. Construction is due to commence July 2017.

Stage 30 – Expected titles July 2018

Stage 30 is located west of Stage 23 and north of the Local Town Centre precinct. Construction is due to commence August 2017.

Active Open Space

Stage 1 of the Active Open Space sports facility comprises of 1 AFL Oval, adventure playground, youth space and car parking. Construction works are progressing well with completion anticipated in June 2017. Stage 2 of the Active Open Space comprises of a second AFL oval and 10 tennis courts and the sporting pavilion with construction completion expected in the 3rd quarter of 2017. The ovals are expected to be ready for use in 2018 following establishment of the playing surface.

Major Play Adventure Park

Construction of the Major Play adventure park is progressing well with completion anticipated in June 2017. Upon completion this destination playground will feature 3 giant treehouses, each connected by rope nets and bridges, slides, swings, an adventure obstacle course and water play zone winding its way through the site!

The carpark construction works are complete, the construction of the pavilion has commenced and landscaping works are well progressed.

What’s happening at Woodlea