Construction Update - July 2018

What a wonderful winter it’s been at Woodlea! We’ve got some very exciting projects underway including planning for the future local Town Centre as well as the extension of Taylors Road, which upon completion will make the connection to Caroline Springs a breeze. With 1,900 residents now calling Woodlea home and another 680 homes under construction, we’ll be growing faster than everyone’s love for Go West’s coffee on a Monday morning! Over the past few months we’ve seen the success of many new community initiatives including monthly resident pizza night's and the AFL Auskick program, with many more exciting events to come - stay tuned.

Stages 2 – 25, 27 and 28 - Titled and settled

Stage 26 - Expected titles September / October 2018
Stage 26 is located south of Stage 24 and abuts the future Local Town Centre to the south. Installation of the services is complete and road pavement installation has commenced.


Stage 29 - Expected titles November 2018
Stage 29 is located north of Stage 32, and east of Stage 30. It also abuts the feature drainage wetland to the east. Watermain installation was recently completed and road pavement installation is about to commence.


Stage 30 - Expected titles November 2018
Stage 30 is located south of Stage 23, north of the Local Town Centre precinct and also comprises the Stage 30 neighbourhood park. Watermain installation was recently completed. Concrete Kerb and footpath works are about to commence.


Stage 31 - Expected titles February 2019
Stage 31 is located directly north of the Deanside Wetlands, south-east of the future Local Town Centre precinct and includes a neighbourhood park. Bulk earthworks are complete, drainage and sewer works are progressing well, and road construction has commenced.


Stage 32 - Expected titles February 2019
Stage 32 is located to the east of Stage 30 and the future Local Town Centre precinct. Drainage works and bulk earthworks are nearing completion and construction of the roads has recently commenced.


Stage 33 - Expected titles April 2019
Stage 33 is located north of Stage 31 and the Deanside Wetlands and east of the future Local Town Centre precinct. Bulk earthworks are nearing completion and sewer works will commence shortly.


Stage 34 - Expected titles June 2019
Stage 34 is located north of Stage 35, east of the of the future Local Town Centre precinct and will also comprise the Stage 34 neighbourhood park. Bulk earthworks are nearly complete and sewer works are due to commence shortly.


Stage 35 - Expected September 2019
Stage 35 is located north of Stage 33 and to the east of the future Local Town Centre precinct. Construction is forecasted to commence in August 2018.


Stage 36 – Expected titles October 2019
Stage 36 is located directly south of the feature drainage wetland. Bulk earthworks are complete and authority approvals are currently being procured to allow construction of the services to commence.


Stage 37 - Expected titles July 2019
Stage 37 is located directly north-west of the future Local Town Centre precinct and north of the Active Open Space playing fields. Bulk earthworks are complete and authority approvals are currently being procured to allow construction of the services to commence.


Stage 38 - Expected titles March 2019
Stage 38 is located north of the Stage 23 raingarden at the intersection of Taylors Road and Frontier Avenue. Stage 38 will contain the new Woodlea Display Village including a feature park. Bulk earthworks are complete, sewer and drainage works progressing well.


Stage 39 – Expected titles December 2019
Stage 39 is located directly east of the future government primary school. Early bulk earthworks for this stage are expected to commence in August.

What’s happening at Woodlea