Thursday 27th July 2017

Construction update - July 2017

Our community continues to grow as construction progresses steadily throughout the site even in the cooler Winter months. We've had a total of 17 stages title and settle with Stage 17 anticipated in August 2017. With over 600 residents now living in Woodlea, we truly feel a sense of community. There is a lot on the horizon including Stage 2 of the Active Open Space Precinct and the Eclipse Early Education Facility anticipated to open early 2018.

Stages 2 – 16 and 19 are titled and settled

Stage 17 - Expected titles August 2017

Stage 17 is located north of the display village, and also abuts Stage 18 to the east. Servicing works are completed. Road surfacing and top-soiling works nearing completion. Consent to register titles is currently being procured from utility authorities and Council.

Stage 18 - Expected titles September 2017

Stage 18 abuts Stage 17 to the west, and both Stages 5 and 16 to the south. Sewer, drainage, electrical and water servicing works are now complete. Kerb and channel works are complete, with road construction works now well progressed. Consent to register titles is currently being procured from utility authorities and Council.

Stage 20 - Expected titles October 2017

Stage 20 is located north of the Local Town Centre and includes a neighbourhood park. Installation of sewer, drainage and are complete. Kerb and channel works are nearing completion and road construction works are well progressed.

Stage 21 - Expected titles October 2017

Stage 21 is located east of Stage 20, and north of the Local Town Centre. Bulk earthworks, sewer and drainage works are complete and water main installation is nearing completion. Road construction has commenced.

Stage 22 - Expected titles November 2017

Stage 22 is located south of Stages 20 and 21, and north of Stage 25 and the Local Town Centre. Sewer and drainage works are now complete. Installation of water and road construction has commenced.

Stage 23 - Expected titles February 2018

Stage 23 is located east of Stage 21, and includes the feature raingarden. Bulk earthworks are now complete. Sewer and drainage works are progressing well.

Stage 24 - Expected titles February 2018

Stage 24 is located in close proximity to the Local Town Centre, south of Stage 23 and north of Stages 26 and 30. Bulk earthworks are now completed and sewer and drainage works have commenced.

Stage 25 – Expected titles March 2018

Stage 25 is located south of Stage 22, and north of the Local Town Centre. Bulk earthworks are now complete. Sewer and drainage works to commence shortly.

Stage 26 - Expected titles May 2018

Stage 26 is located south of Stage 24, and abuts the future Local Town Centre to the south. Bulk earthworks have commenced.

Stage 27 – Expected titles March 2018

Stage 27 is located east of Stage 23 and abuts the Kororoit Creek reserve. Taylors Road is located north of the stage. Bulk earthworks are progressing well.

Stage 28 – Expected titles May 2018

Stage 28 is located east of Stage 23 and 24, and abuts the Kororoit Creek reserve to the east. Stripping works are completed with bulk earthworks to commence.

Stage 29 – Expected titles June 2018

Stage 29 is located north of Stage 32, and east of Stage 30. It also abuts the feature drainage reserve to the east. Construction is due to commence in August 2017.

Stage 30 – Expected titles July 2018

Stage 30 is located west of Stage 23, north of the Local Town Centre precinct and also comprises the Stage 30 neighborhood park. Construction is due to commence August 2017.

Stage 31 – Expected titles October 2018

Stage 30 is located west of Stage 26 and north of the Local Town Centre precinct. Construction is due to commence September 2017.

Active Open Space

Stage 1 of the Active Open Space sports facility comprises of 1 AFL Oval, adventure playground, youth space and car parking. Construction works are now completed.

Stage 2 of the Active Open Space comprises of a second AFL oval and 10 tennis courts and the sporting pavilion with construction completion expected in the 3rd quarter of 2017. The ovals are expected to be ready for use in fourth quarter of 2018 following a 1 year establishment period of the playing surface.

Taylors Road

The first stage of Taylors Road involves the construction of a new single carriageway (one lane in each direction) from Leakes Road to Frontier Avenue adjacent to Stage 18 accessed via a left out/right in intersection.

As part of the project, a new un-signalised Tee-intersection will also be formed on Leakes Road at the entrance to the new Taylors Road. This will involve the widening and reconstruction of Leakes Road on both north and south approaches along with the construction of raised concrete splitter islands and new line markings.

Bulk earthworks are nearing completion with drainage works to commence shortly. The first stage of the project is estimated to be completed in the second quarter of 2018.

Eclipse Early Education Group Childcare Facility

Woodlea has entered into an agreement with Eclipse Early Education Group to deliver a childcare facility, located opposite the Active Open Space in Stage 16, which will accommodate approximately 100 places. The planning permit has been approved and the facility is due to open to the public in the 2nd quarter of 2018.