Wednesday 31st January 2018

Construction update - January 2018

We are thrilled to have started the year with a bang, having received titles for Stage 18, 20 and 21 just in the month of January! Get the full update below:

Stages 2 – 20 are titled and settled

Stage 21 - Titled (Settlement due 13 February 2018)

Stage 22 - Expected titles February 2018

Stage 22 is located south of Stages 20 and 21, and north of Stage 25 and the Local Town Centre. Construction works are complete and consent to register titles is currently being procured from utility authorities and Council.

Stage 23 - Expected titles March 2018

Stage 23 is located east of Stage 21, and includes the feature raingarden. Asphalt, concrete and topsoiling works are progressing well.

Stage 24 - Expected titles April 2018

Stage 24 is located in close proximity to the Local Town Centre, south of Stage 23 and north of Stages 26 and 30. Asphalt, concrete and topsoiling works are commencing shortly.

Stage 25 – Expected titles April 2018

Stage 25 is located south of Stage 22, and north of the Local Town Centre. Water main construction is complete and electrical installation is well progressed.

Stage 26 - Expected titles June 2018

Stage 26 is located south of Stage 24, and abuts the future Local Town Centre to the south. Sewer works are complete and drainage works are progressing well.

Stage 27 – Expected titles April 2018

Stage 27 is located east of Stage 23 and abuts the Kororoit Creek reserve. Taylors Road is located north of the stage. Watermain installation is progressing well and electrical installation is commencing shortly.

Stage 28 – Expected titles May 2018

Stage 28 is located east of Stage 23 and 24, and abuts the Kororoit Creek reserve to the east. Watermain installation is progressing well and electrical installation is commencing shortly.

Stage 29 – Expected titles June 2018

Stage 29 is located north of Stage 32, and east of Stage 30. It also abuts the feature drainage reserve to the east. Sewer works are complete and drainage works are well progressed.

Stage 30 – Expected titles July 2018

Stage 30 is located south of Stage 23, north of the Local Town Centre precinct and also comprises the Stage 30 neighbourhood park. Bulk earthworks are complete and sewer works are well progressed.

Stage 31 – Expected titles December 2018

Stage 31 is located directly north of the Deanside wetlands and south east of the of the future Local Town Centre precinct and also comprises the Stage 31 neighbourhood park. Preliminary earthworks have recently commenced.

Stage 32 – Expected titles January 2019

Stage 32 is located to the east of Stage 30 and the future Local Town Centre precinct. Bulk earthworks is progressing well.

Stage 33 – Expected titles March 2019

Stage 33 is located north of Stage 31 and the Deanside wetlands and to the east of the of the future Local Town Centre precinct. Construction is forecasted to commence in February 2018.

Stage 34 - Expected titles June 2019

Stage 34 is located north of Stage 33 and to the east of the of the future Local Town Centre precinct and also comprises the Stage 34 neighbourhood park. Construction is forecasted to commence in April 2018.

Stage 37 – Expected titles May 2019

Stage 37 is located directly north-west of the future Local Town Centre precinct and north of the Active Open Space Playing fields. Construction is forecasted to commence in May 2018.

Active Open Space

Stage 1 of the Active Open Space precinct comprises of one AFL Oval, adventure playground, youth space and car parking. Construction works are now completed. Stage 2 of the Active Open Space comprises of a second AFL oval and 10 tennis courts and the sporting pavilion with construction completion estimated in early 2018. The ovals are expected to be ready for use in fourth quarter of 2018 following a 1 year establishment period of the grass playing surface.

 

Taylors Road

The first stage of Taylors Road involves the construction of a new single carriageway (one lane in each direction) from Leakes Road to Frontier Avenue adjacent to Stage 18 accessed via a left out/right in intersection. As part of the project, a new un-signalised Tee-intersection will also be formed on Leakes Road at the entrance to the new Taylors Road. This will involve the widening and reconstruction of Leakes Road on both north and south approaches along with the construction of raised concrete splitter islands and new line markings. Pavement construction is well progressed, traffic on Leakes road is expected to be changed over to the new widened eastern carriageway in February to allow construction of the Western carriageway to commence. The first stage of the project is estimated to be completed in the second quarter of 2018. The second stage of the Taylors Road from Frontier Avenue to Fields Street is forecasted to commence shortly.