Tuesday 1st May 2018

Construction Update - April 2018

Stages 2 - 22 are titled and settled  

Stage 23 - Expected titles May/June 2018

Stage 23 is located east of Stage 21 and includes the feature raingarden. Practical Completion has been achieved.  Consent to register titles is currently being procured from utility authorities and Council.

Stage 24 - Expected titles May/June 2018

Stage 24 is located in close proximity to the Local Town Centre, south of Stage 23 and north of Stages 26 and 30. Practical Completion has been achieved.  Consent to register titles is currently being procured from utility authorities and Council.

Stage 25 - Expected titles June2018

Stage 25 is located south of Stage 22, and north of the Local Town Centre. Consent to register titles is currently being procured from utility authorities and Council.

Stage 26 - Expected titles August 2018

Stage 26 is located south of Stage 24, and abuts the future Local Town Centre to the south. Electrical works and road boxing are progressing well.

Stage 27 - Expected titles June 2018

Stage 27 is located east of Stage 23 and abuts the Kororoit Creek reserve. Taylors Road is located north of the stage. Asphalt and concrete works are nearing completion and consent to register titles will shortly be procured from utility authorities and Council.  completion.

Stage 28 - Expected titles June 2018

Stage 28 is located east of Stage 23 and 24, and abuts the Kororoit Creek reserve to the east. Asphalt and concrete works are nearing completion and consent to register titles will shortly be procured from utility authorities and Council. 

Stage 29 - Expected titles August 2018

Stage 29 is located north of Stage 32, and east of Stage 30. It also abuts the feature drainage reserve to the east. Road boxing and watermain installation is progressing well. 

Stage 30 - Expected titles August 2018

Stage 30 is located south of Stage 23, north of the Local Town Centre precinct and also comprises the Stage 30 neighbourhood park. Drainage works are complete and watermain installation is commencing. 

Stage 31 - Expected titles December 2018

Stage 31 is located directly north of the Deanside wetlands, south-east of the future Local Town Centre precinct and also comprises the Stage 31 neighbourhood park. Bulk earthworks are progressing well.

Stage 32 - Expected titles January 2019

Stage 32 is located to the east of Stage 30 and the future Local Town Centre precinct. Drainage works are progressing well.

Stage 33 - Expected titles March 2019

Stage 33 is located north of Stage 31 and the Deanside wetlands, and east of the future Local Town Centre precinct. Bulk earthworks are progressing well.

Stage 34 - Expected titles June 2019

Stage 34 is located north of Stage 35, east of the of the future Local Town Centre precinct and will also comprise the Stage 34 neighbourhood park. Bulk earthworks are progressing well.

Stage 35 - Expected June 2019

Stage 35 is located north of Stage 33, the Deanside wetlands and to the east of the future Local Town Centre precinct. Construction is forecasted to commence in May 2018.

Stage 37 - Expected titles May 2019

Stage 37 is located directly north-west of the future Local Town Centre precinct and north of the Active Open Space playing fields. Construction is forecasted to commence in May 2018.